Lead Government Agency |
Office of the Investment Board & the Ministry of Physical Infrastructure and Transport |
PROJECT DETAILS
|
Project Cost (In USD) |
Line 1: 783.62 Million Line 2: 680.60 Million Line 3:1510.03 Million Line 4:1187.94 Million Line 5:1309.53 Million Total: 5471.72 Million |
|
Progress |
Feasibility Study |
|
Project Documents Available |
Feasibility Study Report |
|
Form of Investment (PPP/Private Investment) |
Public Private Partnership |
|
Expected Fiscal Benefits to GoN |
|
PROJECT DESCRIPTION AND RELEVANCE/ OBJECTIVES
The population of Kathmandu Valley is about 2.5 million, but an estimated population, including the floating population is around 5 million. Most roads in the valley are narrow and traffic congestion is very serious. Therefore, a mass rapid transport system is required in the Kathmandu valley. The road network in the valley is only 1500 km.
RELEVANCE TO THE OVERALL ECONOMY
The construction of metro train in Kathmandu valley is expected to resolve the traffic congestion in the city and catalyze the capital’s economic growth. It will create significant number of employment opportunities and thereby improve the overall livelihood and prosperity.
SALIENT FEATURES OF THE PROJECT
Line 1 (Satdobato- Ratnapark- Narayangopal Chowk)
12.1 km (Elevated)
Stations (Ordinary+Transfer) – 11 (5+6)
Line 2 (Kirtipur- Kalimati- Newbaneshwor- Airport)
11.15 km (Elevated)
Stations (Ordinary+Transfer) – 9 (5+4)
Line 3 (Ringroad)
28.53 km (Elevated)
Stations (Ordinary+Transfer) – 17 (9+8)
Line 4 (Swayambhunath- Dilibazzar- Bouddha)
11.7 km (Underground)
Stations (Ordinary+Transfer) – 10 (6+4)
Line 5 (Dhobighat- Singhadurbar- Naxal- Gongabu)
13.8 km (Underground)
Stations (Ordinary+Transfer) – 10 (4+6)
Total: 77.28 km
Stations (Ordinary +Transfer) – 57 (29+28)