What are the potential models for project development?

As per sub-section 2 of section 17 of PPPI Act, 2019, any project relating to infrastructure may be carried out through the PPP with the following methods;

  1. Build and Transfer (BT)
  2. Build, Operate and Transfer (BOT)
  3. Build, Own, Operate and Transfer (BOOT)
  4. Build, Transfer and Operation (BTO)
  5. Lease, Operation and Transfer (LOT)
  6. Lease, Build, Operate and Transfer (LBOT)
  7. Development, Operation and Transfer (DOT)
  8. Management, Operation and Transfer (MOT)
  9. Rehabilitation, Operation and Transfer (ROT)
  10. Similar other method